2024 Construction Projects

Chillicothe NTIA Grant – Green Hills was awarded the NTIA Grant in March 2022. Construction began in May of 2023. As of May 2024, we have begun installing customers with active connections with a final installation date of July 2024 for all customers.

Braymer/Hamilton ARPA Grant – Green Hills was awarded the ARPA Grant in January 2023. Construction began in Braymer in March of 2024 and will continue through May of 2024. Possible installs may began in July of 2024. Hamilton construction will begin in May of 2024. 

2023 Construction Projects

Chillicothe – CHILLI I, CHILLI O, and CHILLI J are complete.

Chillicothe NTIA Grant – Green Hills was awarded the NTIA Grant in March 2022. While the final details are still in process. Construction began in the Spring of 2023.

Higginsville: The Tracy Addition and Willow Creek are complete.

Mayview (rural): West of Higginsville / north of Mayview is complete.

Reconnect Areas – Construction began in October 2021 and under Reconnect Grant requirements the entire project must be completed by 2025; however, we completed the project early. The U.S. Department of Agriculture (USDA) Reconnect Grant areas include: Utica (Complete), Nettleton (Complete), Rural area South of Hamilton/New York (Complete), Rural area in SW Caldwell County/Mirabile (Complete) and Rural areas North of Chillicothe (Complete).

Stet – Line 1 and 4 are complete.

Bogard – Line 2, 3 and 5 completed.

2022 Construction Projects

Chillicothe – CHILLI I and CHILLI O have been completed and are now enjoying the benefits of fiber. CHILLI J is in the construction stage with most of the installations scheduled for Spring 2022. (weather permitting) The construction has been completed for a portion of CHILLI J, so some installations have started ahead of schedule.

Higginsville: The Tracy Addition and Willow Creek are in the installation stage and anticipating on being finished by the end of the year (weather permitting). 

Mayview (rural): West of Higginsville / north of Mayview is in the installation stage and anticipating being finished by the end of the year (weather permitting).

Reconnect Areas – We have received approval to begin construction for the U.S. Department of Agriculture (USDA) Reconnect Grant. Construction began in October 2021 and under Reconnect Grant requirements the entire project must be completed by 2025; however, we anticipate finishing ahead of that schedule.
Reconnect Areas: Utica, Nettleton (Under Construction), Rural area South of Hamilton/New York, Rural area in SW Caldwell County/Mirabile and Rural areas North of Chillicothe (Under Construction).

Stet – Line 4 is complete. Line 1 is in the construction stage with installations tentatively scheduled for Spring 2022. (weather permitting)