2022 Construction Projects

Chillicothe – CHILLI I and CHILLI O are complete with CHILLI J in the final stages of installation. We anticipate having CHILLI J complete by the end of April 2022. (weather permitting).

Chillicothe NTIA Grant – Green Hills was awarded the NTIA Grant in March 2022. While the final details are still in process, Green Hills anticipates beginning construction on the fiber route late summer 2022.

Higginsville: The Tracy Addition and Willow Creek are complete.

Mayview (rural): West of Higginsville / north of Mayview is complete.

Reconnect Areas – We have received approval to begin construction for the U.S. Department of Agriculture (USDA) Reconnect Grant. Construction began in October 2021 and under Reconnect Grant requirements the entire project must be completed by 2025; however, we anticipate finishing ahead of that schedule.
Reconnect Areas: Utica (Under Construction), Nettleton (Under Construction), Rural area South of Hamilton/New York, Rural area in SW Caldwell County/Mirabile and Rural areas North of Chillicothe (Under Construction).

Stet – Line 1 and 4 are complete.

2021 Construction Projects

Chillicothe – CHILLI I and CHILLI O have been completed and are now enjoying the benefits of fiber. CHILLI J is in the construction stage with most of the installations scheduled for Spring 2022. (weather permitting) The construction has been completed for a portion of CHILLI J, so some installations have started ahead of schedule.

Higginsville: The Tracy Addition and Willow Creek are in the installation stage and anticipating on being finished by the end of the year (weather permitting). 

Mayview (rural): West of Higginsville / north of Mayview is in the installation stage and anticipating being finished by the end of the year (weather permitting).

Reconnect Areas – We have received approval to begin construction for the U.S. Department of Agriculture (USDA) Reconnect Grant. Construction began in October 2021 and under Reconnect Grant requirements the entire project must be completed by 2025; however, we anticipate finishing ahead of that schedule.
Reconnect Areas: Utica, Nettleton (Under Construction), Rural area South of Hamilton/New York, Rural area in SW Caldwell County/Mirabile and Rural areas North of Chillicothe (Under Construction).

Stet – Line 4 is complete. Line 1 is in the construction stage with installations tentatively scheduled for Spring 2022. (weather permitting)